Question 32

You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

Options:

A.

Direct expense

B.

External requirement

C.

Temporary resource

D.

Expert judgment

Discussion
Andrew
Are these dumps helpful?
Jeremiah Nov 9, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Nov 27, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Nov 10, 2025
Great. Yes they are really effective
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Nov 9, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Nov 4, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Question 33

John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

Options:

A.

3000

B.

79

C.

80

D.

3160

Discussion
Question 34

Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

Options:

A.

Cost variances and Cost Performance Index

B.

Scope baseline

C.

Performance measurement baseline

D.

Schedule variances, planned value, and the Schedule Performance Index

Discussion
Question 35

What is the term assigned to graphic in the figure given below?

Questions 35

Options:

A.

Communications bull's eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Discussion