Big Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-SP Exam Questions and Answers by nolan

Page: 9 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: nolan
Question 36

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

Options:

A.

0.98

B.

-$16,677

C.

1.07

D.

0.94

Discussion
Question 37

You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?

Options:

A.

Critical path scheduling

B.

Time-oriented scheduling

C.

Resource-oriented scheduling

D.

Network scheduling

Discussion
Question 38

You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?

Options:

A.

Identify typical schedule milestones.

B.

Create parametric estimates for repetitive activities.

C.

Save time creating activity duration estimates.

D.

Import activity attributes.

Discussion
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Oct 17, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Oct 4, 2025
Yeah, definitely. I experienced the same.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 27, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Robin
Cramkey is highly recommended.
Jonah Oct 26, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Oct 23, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Question 39

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Discussion
Page: 9 / 11

PMI-SP
PDF

$36.75  $104.99

PMI-SP Testing Engine

$43.75  $124.99

PMI-SP PDF + Testing Engine

$57.75  $164.99