Question 36

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

Options:

A.

0.98

B.

-$16,677

C.

1.07

D.

0.94

Discussion
Question 37

You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?

Options:

A.

Critical path scheduling

B.

Time-oriented scheduling

C.

Resource-oriented scheduling

D.

Network scheduling

Discussion
Question 38

You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?

Options:

A.

Identify typical schedule milestones.

B.

Create parametric estimates for repetitive activities.

C.

Save time creating activity duration estimates.

D.

Import activity attributes.

Discussion
Question 39

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Discussion
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Aug 3, 2026
Thanks for the recommendation! I'll check it out.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Aug 24, 2026
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Norah
Cramkey is highly recommended.
Zayan Aug 17, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Aug 8, 2026
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Page: 9 / 11

PMI-SP
PDF

$36.75  $104.99

PMI-SP Testing Engine

$43.75  $124.99

PMI-SP PDF + Testing Engine

$57.75  $164.99