Week End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMI-SP Exam Questions and Answers by nolan

Page: 9 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: nolan
Question 36

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

Options:

A.

0.98

B.

-$16,677

C.

1.07

D.

0.94

Discussion
Question 37

You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?

Options:

A.

Critical path scheduling

B.

Time-oriented scheduling

C.

Resource-oriented scheduling

D.

Network scheduling

Discussion
Question 38

You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?

Options:

A.

Identify typical schedule milestones.

B.

Create parametric estimates for repetitive activities.

C.

Save time creating activity duration estimates.

D.

Import activity attributes.

Discussion
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Dec 20, 2025
That's great to know. So, you think new students should buy these dumps?
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Dec 18, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Dec 9, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Andrew
Are these dumps helpful?
Jeremiah Dec 22, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Question 39

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Discussion
Page: 9 / 11

PMI-SP
PDF

$31.5  $104.99

PMI-SP Testing Engine

$37.5  $124.99

PMI-SP PDF + Testing Engine

$49.5  $164.99