Question 12

Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

Options:

A.

Records Management System

B.

Performance reporting

C.

Inspection and Audit

D.

Payment System

Discussion
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Aug 29, 2024
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Sep 22, 2024
That's great to hear. I am going to try them soon.
Question 13

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.

Project change control process

B.

Perform integrated change control process

C.

Configuration management

D.

Communications management

Discussion
Question 14

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?

Options:

A.

$163,626

B.

$130,901

C.

-$985,040

D.

0.16

Discussion
Question 15

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should be at the 45 percent milestone today, but due to some early delays you're running late. What is the planned value of your project?

Options:

A.

$950,000

B.

$2,375,000