Question 20

What project management plan will document the time frame and frequency for the distribution of required information?

Options:

A.

Scope Management Plan

B.

Communications Management Plan

C.

Stakeholder Management Plan

D.

Schedule Management Plan

Discussion
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Oct 15, 2025
That's great. I think I'll give Cramkey Dumps a try.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Oct 21, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Inaaya
Are these Dumps worth buying?
Fraser Oct 5, 2025
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Oct 25, 2025
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Question 21

You are the project manager of the NGG Project. This project will be using a new material that the project team has never worked with before. You'd like to use some preventive action to ensure that the installation of the new materials is successful in the project. Which one of the following project actions is an example of the best preventive action for this project?

Options:

A.

Hire a subject matter expert to train the project team how to install the materials.

B.

Purchase additional materials so in case the team wastes materials during their installation.

C.

Hire a subject matter expert to install the new materials.

D.

Create incentive by rewarding the project team if they don't waste the materials.

Discussion
Question 22

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

Options:

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Discussion
Question 23

You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?

Options:

A.

Project document updates

B.

Expert judgment

C.

Performance report

D.

Project management plan updates