Question 20

What project management plan will document the time frame and frequency for the distribution of required information?

Options:

A.

Scope Management Plan

B.

Communications Management Plan

C.

Stakeholder Management Plan

D.

Schedule Management Plan

Discussion
Question 21

You are the project manager of the NGG Project. This project will be using a new material that the project team has never worked with before. You'd like to use some preventive action to ensure that the installation of the new materials is successful in the project. Which one of the following project actions is an example of the best preventive action for this project?

Options:

A.

Hire a subject matter expert to train the project team how to install the materials.

B.

Purchase additional materials so in case the team wastes materials during their installation.

C.

Hire a subject matter expert to install the new materials.

D.

Create incentive by rewarding the project team if they don't waste the materials.

Discussion
Question 22

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

Options:

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Discussion
Question 23

You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?

Options:

A.

Project document updates

B.

Expert judgment

C.

Performance report

D.

Project management plan updates

Discussion
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Dec 5, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Dec 11, 2025
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Dec 6, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Dec 20, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Norah
Cramkey is highly recommended.
Zayan Dec 22, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Page: 5 / 11

PMI-SP
PDF

$31.5  $104.99

PMI-SP Testing Engine

$37.5  $124.99

PMI-SP PDF + Testing Engine

$49.5  $164.99