Question 20

What project management plan will document the time frame and frequency for the distribution of required information?

Options:

A.

Scope Management Plan

B.

Communications Management Plan

C.

Stakeholder Management Plan

D.

Schedule Management Plan

Discussion
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Dec 18, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Dec 4, 2025
They give you a competitive edge and help you prepare better.
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Dec 16, 2025
Me too. They're a lifesaver!
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Dec 21, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Dec 8, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Question 21

You are the project manager of the NGG Project. This project will be using a new material that the project team has never worked with before. You'd like to use some preventive action to ensure that the installation of the new materials is successful in the project. Which one of the following project actions is an example of the best preventive action for this project?

Options:

A.

Hire a subject matter expert to train the project team how to install the materials.

B.

Purchase additional materials so in case the team wastes materials during their installation.

C.

Hire a subject matter expert to install the new materials.

D.

Create incentive by rewarding the project team if they don't waste the materials.

Discussion
Question 22

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

Options:

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Discussion
Question 23

You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?

Options:

A.

Project document updates

B.

Expert judgment

C.

Performance report

D.

Project management plan updates

Discussion