PMI Updated PMI-SP Exam Questions and Answers by alicja

Page: 5 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: alicja
Question 20

What project management plan will document the time frame and frequency for the distribution of required information?

Options:

A.

Scope Management Plan

B.

Communications Management Plan

C.

Stakeholder Management Plan

D.

Schedule Management Plan

Discussion
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Sep 25, 2024
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 21

You are the project manager of the NGG Project. This project will be using a new material that the project team has never worked with before. You'd like to use some preventive action to ensure that the installation of the new materials is successful in the project. Which one of the following project actions is an example of the best preventive action for this project?

Options:

A.

Hire a subject matter expert to train the project team how to install the materials.

B.

Purchase additional materials so in case the team wastes materials during their installation.

C.

Hire a subject matter expert to install the new materials.

D.

Create incentive by rewarding the project team if they don't waste the materials.

Discussion
Question 22

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

Options:

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Discussion
Question 23

You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?

Options:

A.

Project document updates

B.

Expert judgment

C.

Performance report

D.

Project management plan updates

Discussion