New Year Special 75% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 75brite

PMI Updated PMI-SP Exam Questions and Answers by elora

Page: 10 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: elora
Question 40

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

Options:

A.

Scope of statement

B.

Project charter

C.

Statement of work (SOW)

D.

WBS

Discussion
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Dec 6, 2025
Thanks for the recommendation! I'll check it out.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Dec 3, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Dec 21, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Dec 25, 2025
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Dec 22, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Question 41

Once the project's WBS has been created what process may happen next?

Options:

A.

Estimate activity resources

B.

Define activities

C.

Estimate activity durations

D.

Sequence activities

Discussion
Question 42

You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?

Options:

A.

300

B.

50

C.

600

D.

25

Discussion
Question 43

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Discussion
Page: 10 / 11

PMI-SP
PDF

$26.25  $104.99

PMI-SP Testing Engine

$31.25  $124.99

PMI-SP PDF + Testing Engine

$41.25  $164.99