New Year Special 75% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 75brite

PMI Updated PMI-SP Exam Questions and Answers by elora

Page: 10 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: elora
Question 40

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

Options:

A.

Scope of statement

B.

Project charter

C.

Statement of work (SOW)

D.

WBS

Discussion
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Dec 22, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Dec 3, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Dec 19, 2025
Yeah, definitely. I experienced the same.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Dec 28, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Question 41

Once the project's WBS has been created what process may happen next?

Options:

A.

Estimate activity resources

B.

Define activities

C.

Estimate activity durations

D.

Sequence activities

Discussion
Question 42

You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?

Options:

A.

300

B.

50

C.

600

D.

25

Discussion
Question 43

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Discussion
Page: 10 / 11

PMI-SP
PDF

$26.25  $104.99

PMI-SP Testing Engine

$31.25  $124.99

PMI-SP PDF + Testing Engine

$41.25  $164.99