PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: reagan
Question 28

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you're running late. What is the schedule variance of your project?

Options:

A.

-$29,350

B.

-$117,282

C.

-$938,260

D.

-$11,740

Discussion
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 31, 2024
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 26, 2024
That's great to know. So, you think new students should buy these dumps?
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Question 29

Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

Options:

A.

Precedence Diagramming Method

B.

Schedule network template

C.

Dependency determination

D.

Activity on the Node

Discussion
Question 30

Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule. Which of the following is a tool and technique for the Schedule Development process?

Options:

A.

Schedule compression

B.

Reserve analysis

C.

Variance analysis

D.

Expert judgment

Discussion
Question 31

Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

Options:

A.

Lesson learned documentation

B.

Risk analysis

C.

Preventive action

D.

Corrective action

Discussion
Page: 7 / 11