Question 40

You are the Scrum Master for four Scrum Teams working from the same Product Backlog

Several of the Developers come to you complaining that work identified for the upcoming two

Sprints will require full-time commitment from a specialist who is external to the teams.

What should the Scrum Master consider in this situation?

(choose the best two answers)

Options:

A.

The need to have enough work to keep all Developers busy.

B.

The benefit of Developers figuring out a solution for themselves.

C.

The desire to maintain a stable velocity.

D.

The ability of the Scrum Teams to produce integrated Increments.

Discussion
Question 41

When multiple Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?

(choose the best answer)

Options:

A.

Yes, in order to accurately inspect what is done.

B.

Yes, but only for Scrum Teams whose work has dependencies.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Discussion
Question 42

Which approach is best for Scrum Teams in order to produce valuable Increments?

(choose the best answer)

Options:

A.

Each Developer works on the component where they feel that they can contribute.

B.

Each Scrum Team works on an independent set of components.

C.

Each Scrum Team is accountable for developing functionality from beginning to end.

D.

Each Scrum Member works only as an independent layer of the system.

Discussion
Question 43

Which three of the following are true about Scrum?

(choose the best three answers)

Options:

A.

Scrum implements self-management by replacing Project Managers with Scrum

Masters.

B.

Scrum is based on empiricism and lean thinking.

C.

Scrum is a framework for developing and sustaining complex products.

D.

Scrum is a methodology where you can pick and choose which parts of Scrum

you think will work for your environment.

E.

Each component of Scrum serves a specific purpose and is essential to Scrum's

success and your usage of Scrum to develop complex products.

Discussion
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Sep 26, 2024
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Sep 28, 2024
did you use PDF or Engine? Which one is most useful?
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Page: 10 / 13

PSPO-I
PDF

$36.75  $104.99

PSPO-I Testing Engine

$43.75  $124.99

PSPO-I PDF + Testing Engine

$57.75  $164.99