Question 24

What is the timebox for the Sprint Review?

(choose the best answer)

Options:

A.

2 hours for a one-month Sprint.

B.

1 day.

C.

4 hours for a one-month Sprint.

D.

As long as needed.

Discussion
Question 25

What does it mean to say that an event has a timebox?

(choose the best answer)

Options:

A.

The event can take no more than a maximum amount of time.

B.

The event must take at least a minimum amount of time.

C.

The event must happen by a given time.

D.

The event must happen at a set time.

Discussion
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Aug 20, 2024
Me too. They're a lifesaver!
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 4, 2024
YES….. I saw the same questions in the exam.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Question 26

The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should:

(choose the best answer)

Options:

A.

Tell the Developers to fit the report into the Sprint Backlog.

B.

Ask the Product Owner to send the manager the report.

C.

Create and deliver the report to the manager herself.

D.

Tell the Scrum Team to figure it out themselves.

E.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

Discussion
Question 27

For the purpose of transparency, when does Scrum say a valuable and useful Increment must

be available?

(choose the best answer)

Options:

A.

At the end of every Sprint.

B.

Every 3 Sprints.

C.

Before the Release Sprint.

D.

After the Acceptance Testing phase.

E.

When the Product Owner asks to create one.