Scrum Updated PSPO-I Exam Questions and Answers by samson

Page: 8 / 13

Scrum PSPO-I Exam Overview :

Exam Name: Professional Scrum Product Owner (PSPO I) Exam
Exam Code: PSPO-I Dumps
Vendor: Scrum Certification: PSPO
Questions: 177 Q&A's Shared By: samson
Question 32

Which of the following are criteria to order Product Backlog items?

(choose all that apply)

Options:

A.

Value of Product Backlog items.

B.

Dependencies between Product Backlog items.

C.

Dependencies to other products.

D.

The availability of the Scrum Master.

E.

All of the above.

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 18, 2024
That sounds really useful. I'll definitely check it out.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Sep 22, 2024
That's great to hear. I am going to try them soon.
Question 33

How is management that is external to the Scrum Team involved in the Daily Scrum?

(choose the best answer)

Options:

A.

The Product Owner represents their opinions.

B.

The Scrum Master speaks on their behalf.

C.

Managers are not required at the Daily Scrum.

D.

Management gives an update at the start of each Daily Scrum.

Discussion
Question 34

True or False: Multiple Scrum Teams working on the same product must have the same Sprint

start date.

Options:

A.

True

B.

False

Discussion
Question 35

Who is accountable for managing the progress of work during a Sprint?

(choose the best answer)

Options:

A.

The Developers.

B.

The most junior member of the team.

C.

The Scrum Master.

D.

The Product Owner.

Discussion