Question 16

A Scrum Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what done means.

(choose the best two answers)

Options:

A.

No work is left to meet the Definition of Done.

B.

Whatever the Product Owner defines as quality.

C.

Ready for integration.

D.

Ready to be released to end users.

E.

All work the Developers are willing to do.

Discussion
Question 17

A Product Backlog is:

(choose the best three answers)

Options:

A.

An exhaustive list of upfront approved requirements to be implemented.

B.

Managed by the Product Owner.

C.

An inventory of things to be done for the Product.

D.

Ordered based on priority, value, dependencies, and risk.

E.

Only visible to the Product Owner and stakeholders.

Discussion
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia (not set)
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper (not set)
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden (not set)
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik (not set)
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Question 18

What are the two responsibilities of testers in a Scrum Team?

(choose the best two answers)

Options:

A.

Tracking quality metrics.

B.

Scrum has no "tester" role.

C.

Verifying the work of programmers.

D.

The Developers are responsible for quality.

E.

Finding bugs.

Discussion
Question 19

The "cone of uncertainty" can be used to do what?

(choose the best answer)

Options:

A.

Determine whether to cut quality, similar to the "Iron Triangle" of project

management.

B.

Determine the cost of a project before it begins.

C.

Illustrate that as a project forecast lengthens, it is increasingly less certain.

D.

Determine the length of the next Sprint.