Scrum Updated PSPO-I Exam Questions and Answers by elle

Page: 5 / 13

Scrum PSPO-I Exam Overview :

Exam Name: Professional Scrum Product Owner (PSPO I) Exam
Exam Code: PSPO-I Dumps
Vendor: Scrum Certification: PSPO
Questions: 177 Q&A's Shared By: elle
Question 20

Which best describes the Product Backlog?

(choose the best answer)

Options:

A.

It is allowed to grow and change as more is learned about the product and its

customers.

B.

It contains all foreseeable tasks and requirements from which the Scrum Team can

develop and maintain a complete project plan.

C.

It provides just enough information to enable a Scrum Team to start the design phase

of a product.

D.

It is baselined to follow change management processes.

Discussion
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia (not set)
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan (not set)
That’s great!!! I’ll definitely give it a try. Thanks!!!
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia (not set)
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey (not set)
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper (not set)
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Question 21

What three things might a Scrum Product Owner focus on to ensure the product delivers value?

(choose the best three answers)

Options:

A.

How much of the functionality of the product is being used.

B.

Direct customer feedback.

C.

How quickly or easily the product can be absorbed and used by its customers.

D.

Velocity is increasing over time.

E.

Minimizing changes to project scope.

Discussion
Question 22

Who is accountable for tracking the remaining work toward the Sprint Goal?

(choose the best answer)

Options:

A.

The Developers.

B.

The Project Manager.

C.

The Product Owner.

D.

The Scrum Master.

Discussion
Question 23

Which three of the following are feedback loops in Scrum?

(choose the best three answers)

Options:

A.

Sprint Review.

B.

Refinement Meeting.

C.

Daily Scrum.

D.

Sprint Retrospective.

E.

Release Planning.

Discussion