Question 52

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Discussion
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Sep 28, 2024
did you use PDF or Engine? Which one is most useful?
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Oct 22, 2024
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Sep 11, 2024
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Question 53

What is the number of stakeholders, if the project has 28 potential communication channels?

Options:

A.

7

B.

8

C.

14

D.

16

Discussion
Question 54

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

Options:

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Discussion
Question 55

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio

B.

Process

C.

Project

D.

Program

Discussion