PMI Updated PMI-001 Exam Questions and Answers by zane

Page: 5 / 34

PMI PMI-001 Exam Overview :

Exam Name: Project Management Professional v5
Exam Code: PMI-001 Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 918 Q&A's Shared By: zane
Question 20

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Discussion
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Dec 11, 2025
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Dec 2, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Dec 26, 2025
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Dec 4, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Question 21

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Discussion
Question 22

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Discussion
Question 23

Organizations manage portfolios based on which of the following types of plans?

Options:

A.

Strategic

B.

Project

C.

Program

D.

Operational

Discussion
Page: 5 / 34
Title
Questions
Posted

PMI-001
PDF

$31.5  $104.99

PMI-001 Testing Engine

$37.5  $124.99

PMI-001 PDF + Testing Engine

$49.5  $164.99