Question 112

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Discussion
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Aug 31, 2024
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Sep 13, 2024
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Question 113

In which of the following types of organizations is resource availability moderate to high?

Options:

A.

Weak matrix

B.

Balanced matrix

C.

Strong matrix

D.

Projectized

Discussion
Question 114

Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV?

Options:

A.

-8000

B.

-2000

C.

2000

D.

8000

Discussion
Question 115

Organizational process assets can be divided into which of the following two categories?

Options:

A.

Project files and corporate knowledge base

B.

Templates, and processes and procedures

C.

Standards, and processes and procedures

D.

Corporate knowledge base and processes and procedures

Discussion
Page: 28 / 34
Title
Questions
Posted

PMI-001
PDF

$36.75  $104.99

PMI-001 Testing Engine

$43.75  $124.99

PMI-001 PDF + Testing Engine

$57.75  $164.99