Question 112

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Dec 17, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Dec 2, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Dec 15, 2025
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Dec 6, 2025
Thanks for the recommendation! I'll check it out.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Dec 4, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Question 113

In which of the following types of organizations is resource availability moderate to high?

Options:

A.

Weak matrix

B.

Balanced matrix

C.

Strong matrix

D.

Projectized

Discussion
Question 114

Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV?

Options:

A.

-8000

B.

-2000

C.

2000

D.

8000

Discussion
Question 115

Organizational process assets can be divided into which of the following two categories?

Options:

A.

Project files and corporate knowledge base

B.

Templates, and processes and procedures

C.

Standards, and processes and procedures

D.

Corporate knowledge base and processes and procedures

Discussion
Page: 28 / 34
Title
Questions
Posted

PMI-001
PDF

$31.5  $104.99

PMI-001 Testing Engine

$37.5  $124.99

PMI-001 PDF + Testing Engine

$49.5  $164.99