Question 76

What type of project structure is a hierarchically organized depiction of the resources by type?

Options:

A.

Organizational breakdown structure (OBS)

B.

Resource breakdown structure (RBS)

C.

Work breakdown structure (WBS)

D.

Project breakdown structure (PBS)

Discussion
Question 77

Which of the following processes are part of the Project Integration Management Knowledge Area?

Options:

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

Discussion
Question 78

Identify Risks is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Discussion
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Aug 30, 2024
That’s great!!! I’ll definitely give it a try. Thanks!!!
Nell
Are these dumps reliable?
Ernie Oct 10, 2024
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 16, 2024
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 31, 2024
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 79

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.