Question 64

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

Options:

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Discussion
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Aug 30, 2024
That’s great!!! I’ll definitely give it a try. Thanks!!!
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Oct 17, 2024
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 31, 2024
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Question 65

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

Options:

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Discussion
Question 66

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

Options:

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Discussion
Question 67

Technical capability, past performance, and intellectual property rights are examples of:

Options:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Discussion