Question 124

An output of the Manage Project Team process is:

Options:

A.

project management plan updates

B.

project staff assignments updates

C.

team performance assessments

D.

resource calendar updates

Discussion
Question 125

Which grid shows which resources are tied to work packages?

Options:

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Project assignment chart

D.

Personnel assignment matrix

Discussion
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 26, 2024
Thanks for the recommendation! I'll check it out.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Oct 17, 2024
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Aug 30, 2024
That’s great!!! I’ll definitely give it a try. Thanks!!!
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Question 126

The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:

Options:

A.

interview technique

B.

information gathering technique

C.

Delphi technique

D.

feedback technique

Discussion
Question 127

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.