Question 48

The quality management plan documents how the project team will implement the quality policy.

It must address all of the following except which one?

Options:

A.

Continuous process improvement

B.

Quality assurance

C.

Quality control

D.

Quality checklists

Discussion
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Aug 29, 2024
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Madeleine
Passed my exam with my dream scoreā€¦. Guys do give these dumps a try. They are authentic.
Ziggy Sep 3, 2024
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Question 49

The performing organization is trying to decide whether to split the contracts department and assign procurement responsibilities to departments directly responsible for the projects. A procurement professional might not want this split to occur because they would lose ___________ in a decentralized contracting environment.

Options:

A.

Standardized company project management practices

B.

Loyalty to the project

C.

Experience

D.

Access to others with similar expertise

Discussion
Question 50

You are a project manager for the Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000, with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months.

Which project should you recommend?

Options:

A.

Project Fish'n for Chips, because the costs on Project Picnic are unknown.

B.

Project Picnic, because Project Fish'n for Chips' payback period is two months longer than Project Picnic's.

C.

Project Picnic, because Project Fish'n for Chips' payback period is four months longer than Project Picnic's.

D.

Project Fish'n for Chips, because its payback period is two months shorter than Project Picnic's.

Discussion
Question 51

Root Cause Analysis related to ________.

Options:

A.

Process Analysis

B.

Performance Measurements

C.

All of the other alternatives apply

D.

Quality Audits