Question 80

Which of the following is not true for a Responsibility Assignment Matrix (RAM)?

Options:

A.

Defines what project member is responsible for each activity

B.

Defines all people associated with each activity

C.

Defines responsibilities for each WBS component

D.

All of the other alternatives apply

Discussion
Question 81

Advantages of the functional (hierarchical) form of organization include _____ and creation of technical competence.

Options:

A.

Single voice to customers

B.

High information processing capability

C.

Ease of horizontal coordination

D.

Clearly defined authority

Discussion
Andrew
Are these dumps helpful?
Jeremiah Oct 27, 2024
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Aug 30, 2024
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Question 82

All of the following are tools and techniques of the Contract Administration process except for which one?

Options:

A.

Contract change control system, buyer-conducted performance review, and inspections and audits

B.

Records management system and information technology

C.

Contract performance information gathering and contract reporting systems

D.

Performance reporting, payment system, and claims administration

Discussion
Question 83

Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Qualitative risk analysis

B.

Quantitative risk analysis

C.

Risk management planning

D.

Risk response planning