Question 64

Quality and credibility of the qualitative risk analysis process requires that different levels of the risk's probabilities and impacts be defined is the definition of what?

Options:

A.

Risk breakdown structure (RBS)

B.

Risk probability and impact

C.

Qualitative risk analysis

D.

Risk response planning

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 15, 2024
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 4, 2024
YES….. I saw the same questions in the exam.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Question 65

Final product transition is an output of which process?

Options:

A.

Direct and Manage Project Execution

B.

Close Project or Phase

C.

Perform Integrated Change Control

D.

Monitor and Control Project Work

Discussion
Question 66

Communication plays a major role in:

Options:

A.

Organizing

B.

Controlling

C.

All of the other alternatives apply

D.

Directing

E.

Planning

Discussion
Question 67

Which of the following MUST NOT performed in project initiation process?

Options:

A.

identify the requirements.

B.

identify business need.

C.

create project scope statement.

D.

create project charter.