BCS ISEB-PM1 Exam Overview :

Exam Name: BCS Foundation Certificate in IS Project Management
Exam Code: ISEB-PM1 Dumps
Vendor: BCS Certification: Project & programme management and consultancy certifications
Questions: 625 Q&A's Shared By: winter
Question 40

In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?

Options:

A.

All of the other alternatives apply

B.

Employees spend only a short amount of time assigned to the project

C.

Not working directly with the assigned functional employees

D.

Not being knowledgeable enough to evaluate employees on technical judgment

E.

Both 1) Not working directly with the assigned functional employees, and 2) Employees spend only a short amount of time assigned to the project.

Discussion
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Dec 4, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Dec 21, 2025
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Dec 28, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Dec 20, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Question 41

Which process group defines the course of action required to attain the objectives that the project was undertaken to achieve?

Options:

A.

Initiating

B.

Executing

C.

Planning

D.

Monitoring and Controlling

Discussion
Question 42

A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?

Options:

A.

Closing

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Discussion
Question 43

In which of the following is the cost of risk hidden by the contractor?

Options:

A.

Fixed Price Plus Incentive

B.

Firm Fixed Price Contract and Fixed Price Plus Incentive

C.

Firm Fixed Price Contract

D.

Cost Plus Percentage of Cost

E.

Cost Plus Fixed Price

Discussion