Question 40

In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?

Options:

A.

All of the other alternatives apply

B.

Employees spend only a short amount of time assigned to the project

C.

Not working directly with the assigned functional employees

D.

Not being knowledgeable enough to evaluate employees on technical judgment

E.

Both 1) Not working directly with the assigned functional employees, and 2) Employees spend only a short amount of time assigned to the project.

Discussion
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Dec 22, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Dec 28, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Dec 6, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Dec 18, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Andrew
Are these dumps helpful?
Jeremiah Dec 22, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Question 41

Which process group defines the course of action required to attain the objectives that the project was undertaken to achieve?

Options:

A.

Initiating

B.

Executing

C.

Planning

D.

Monitoring and Controlling

Discussion
Question 42

A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?

Options:

A.

Closing

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Discussion
Question 43

In which of the following is the cost of risk hidden by the contractor?

Options:

A.

Fixed Price Plus Incentive

B.

Firm Fixed Price Contract and Fixed Price Plus Incentive

C.

Firm Fixed Price Contract

D.

Cost Plus Percentage of Cost

E.

Cost Plus Fixed Price

Discussion