Question 32

Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

Options:

A.

Perform Quality Control

B.

Quality Policy

C.

Perform Quality Assurance

D.

Quality Planning

Discussion
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Aug 6, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Aug 21, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Aug 5, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Aug 20, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Aug 3, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Question 33

A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the average labor hours per installation from past projects to predict the future.

This is an example of which of the following?

Options:

A.

Parametric estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Monte Carlo analysis

Discussion
Question 34

A ________ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

Options:

A.

Parametric

B.

Bottom up.

C.

Budget

D.

Top down.

E.

Definitive.

Discussion
Question 35

The use of group creativity techniques as a tool and technique is done in which of the following processes?

Options:

A.

Plan Quality

B.

Collect Requirements

C.

Define Scope

D.

Perform Quality Control

Discussion