Question 32

Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

Options:

A.

Perform Quality Control

B.

Quality Policy

C.

Perform Quality Assurance

D.

Quality Planning

Discussion
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 3, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Nov 14, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Nov 21, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Nov 12, 2025
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Nov 15, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Question 33

A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the average labor hours per installation from past projects to predict the future.

This is an example of which of the following?

Options:

A.

Parametric estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Monte Carlo analysis

Discussion
Question 34

A ________ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

Options:

A.

Parametric

B.

Bottom up.

C.

Budget

D.

Top down.

E.

Definitive.

Discussion
Question 35

The use of group creativity techniques as a tool and technique is done in which of the following processes?

Options:

A.

Plan Quality

B.

Collect Requirements

C.

Define Scope

D.

Perform Quality Control

Discussion
Page: 8 / 23