Question 32

Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

Options:

A.

Perform Quality Control

B.

Quality Policy

C.

Perform Quality Assurance

D.

Quality Planning

Discussion
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 9, 2024
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 16, 2024
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Sep 22, 2024
That's great to hear. I am going to try them soon.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Aug 29, 2024
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Question 33

A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the average labor hours per installation from past projects to predict the future.

This is an example of which of the following?

Options:

A.

Parametric estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Monte Carlo analysis

Discussion
Question 34

A ________ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

Options:

A.

Parametric

B.

Bottom up.

C.

Budget

D.

Top down.

E.

Definitive.

Discussion
Question 35

The use of group creativity techniques as a tool and technique is done in which of the following processes?

Options:

A.

Plan Quality

B.

Collect Requirements

C.

Define Scope

D.

Perform Quality Control

Discussion