Question 44

The LEED AP is leading the first design charrette for a new LEED project with the project's owners. What document should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner's Project Requirements (OPR)

B.

Owner's list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Discussion
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 15, 2024
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 16, 2024
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Oct 22, 2024
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Oct 5, 2024
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 45

A comprehensive rainwater management plan may include design elements such as

Options:

A.

artificial turf, bioretention pond, cisterns and hay bales

B.

cisterns, porous pavement, swales and vegetated roofs

C.

soil compaction, swales, vegetated roofs and xeriscaping

D.

bioretention pond, cisterns, porous pavement and stabilized construction entrance

Discussion
Question 46

What is the minimum gross floor area required for a Building Design and Construction project to be eligible for

certification?

Options:

A.

250 ft2 (23 m2)

B.

500 ft2 (46 m2)

C.

750 ft2 (70 m2)

D.

1000 ft2 (93 m2)

Discussion
Question 47

Which of the following statements are true for Erosion and Sedimentation Control (ESC) plan prerequisite compliance?

Options:

A.

The ESC plan cannot be modified during the design phase of the LEED certification

B.

The ESC plan can be developed or modified during the design phase of LEED certification

C.

A compliant ESC plan may be developed during construction

D.

A compliant ESC plan must be in place when the commissioning authority is appointed

Discussion