Exam Name: | ISTQB Certified Tester Foundation Level (Syllabus 2018) | ||
Exam Code: | CTFL_Syll2018 Dumps | ||
Vendor: | iSQI | Certification: | CTFL2018 |
Questions: | 365 Q&A's | Shared By: | margaux |
Refer to the exhibit
The following test cases need to be run, but time is limited, and it is possible that not all will be completed before the end of the test window
The first activity is to run any re-tests, followed by the regression test script. Users have supplied their priority order to tests.
Which of the following gives an appropriate test execution schedule, taking account of the prioritisation and other constraints? [K3]
Dynamic Analysis Tools are used to: