Question 76

Tests have been specified for the latest software release and users have prioritised these.

However, there are some dependencies between tests as shown in the table below (e.g. Test ID. ‘123’ cannot be run until Test ID. ‘456’ has been successfully completed).

Questions 76

Which test execution schedule best meets the prioritisation and dependency conditions?

Options:

A.

3, 5, 7, 10, 2, 4, 6, 8, 9, 1.

B.

5, 7, 4, 3, 9, 10, 1, 6, 8, 2.

C.

6, 1, 2, 9, 4, 3, 5, 7, 8, 10.

D.

1, 4, 3, 5, 2, 7, 9, 10, 6, 8.

Discussion
Question 77

A "functional test" is...

Options:

A.

... a test focused on the efficiency of the system

B.

... a dynamic test for which the tests are based on the specification of the test object.

C.

... a static comparison of test and requirements specification of a test object

D.

... a test for which the test cases and test data are based on the structure of the test object

Discussion
Question 78

During the development of a software change for a system, the developer makes a mistake in his work, which leads to a fault in the code. Unfortunately the fault is not found by software testing and is released into live.

What is the definite consequence of this mistake?

Options:

A.

The system will fail, causing a defect

B.

If the contained in a small, the system may fail

C.

Loss of money, time, or business reputation

D.

Contractual requirements have not been met by testing

Discussion
Question 79

Which one of the following would you typically expect to find in a test completion report for a test level?

Options:

A.

Factors that are currently impeding test progress and the tests planned for the following day.

B.

A summary of the testing performed and any deviations from the schedule, duration or effort of test activities.

C.

The planned overall approach for testing and the resources required to perform the various test activities.

D.

The proposed exit criteria and metrics reports for review and agreement by the stakeholders.

Discussion
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Aug 27, 2024
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 2, 2024
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Robin
Cramkey is highly recommended.
Jonah Oct 16, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Sep 13, 2024
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Page: 19 / 27
Title
Questions
Posted

CTFL_Syll2018
PDF

$36.75  $104.99

CTFL_Syll2018 Testing Engine

$43.75  $124.99

CTFL_Syll2018 PDF + Testing Engine

$57.75  $164.99