Exam Name: | ISTQB Certified Tester Foundation Level (Syllabus 2018) | ||
Exam Code: | CTFL_Syll2018 Dumps | ||
Vendor: | iSQI | Certification: | CTFL2018 |
Questions: | 365 Q&A's | Shared By: | emilio |
Tests have been specified for the latest software release and users have prioritised these.
However, there are some dependencies between tests as shown in the table below (e.g. Test ID. ‘123’ cannot be run until Test ID. ‘456’ has been successfully completed).
Which test execution schedule best meets the prioritisation and dependency conditions?
During the development of a software change for a system, the developer makes a mistake in his work, which leads to a fault in the code. Unfortunately the fault is not found by software testing and is released into live.
What is the definite consequence of this mistake?
Which one of the following would you typically expect to find in a test completion report for a test level?