Question 8

Which TWO of the following test tools would be classified as test execution tools? [K2]

a. Test data preparation tools

b. Test harness

c. Review tools

d. Test comparators

e. Configuration management tools

Options:

A.

a and b

B.

c and d

C.

c and e

D.

b and d

Discussion
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Aug 29, 2024
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Question 9

What content would be in an incident report if that incident report was based on the IEEE 829 Standard for SoftwareTest Documentation?

(i)Identification of configuration items of the software or system.

(ii)Software or system lifecycle process in which the incident was observed.

(iii)Description of the anomaly to enable reproduction of the incident.

(iv)Number of occurrences of the incident.

(v)Classification of the cause of the incident for metrics and for reporting purposes.

Number of correct answers: 1

Options:

A.

i, ii, iii

B.

ii, iii

C.

i, iii, iv

D.

i, ii, iii, v

Discussion
Question 10

Which of the following BEST describes the relationship between test planning and test execution? [K2]

Options:

A.

Test planning ensures the level of detail in test procedures is appropriate for test execution

B.

Test planning schedules test execution but does not assign resources

C.

Test planning defines the overall approach to testing but does not schedule specific activities such as test execution

D.

Test planning identifies test objectives related to scope and risk but does not define the level of detail for test procedures used in test execution

Discussion
Question 11

Which of the following test cases will ensure that the statement ‘Print ‘Hold’’ is exercised? [K3]

Refer to the exhibit

Questions 11

Options:

A.

X=2, Y=2, Z=2

B.

X=2, Y=3, Z=4

C.

X=2, Y=4, Z=3

D.

X=4, Y=3, Z=2

Discussion
Page: 2 / 27
Title
Questions
Posted

CTFL_Syll2018
PDF

$36.75  $104.99

CTFL_Syll2018 Testing Engine

$43.75  $124.99

CTFL_Syll2018 PDF + Testing Engine

$57.75  $164.99