Question 60

A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?

Options:

A.

Too much time might be spent generating project delays.

B.

The project manager might be seen as weak.

C.

The number of change requests throughout the project might be reduced.

D.

Some stakeholders might not be completely satisfied.

Discussion
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 31, 2024
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Nell
Are these dumps reliable?
Ernie Oct 10, 2024
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Oct 17, 2024
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Sep 22, 2024
That's great to hear. I am going to try them soon.
Question 61

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

Options:

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Discussion
Question 62

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Discussion
Question 63

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Discussion
Page: 15 / 21