Question 80

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

Options:

A.

Encryption

B.

Multifactor authentication

C.

Quality assurance

D.

Password protection

Discussion
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Sep 28, 2024
did you use PDF or Engine? Which one is most useful?
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Robin
Cramkey is highly recommended.
Jonah Oct 16, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Question 81

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

Options:

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Discussion
Question 82

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Discussion
Question 83

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Options:

A.

Notify customers the downtime will take longer than expected.

B.

Add new team members to help speed up validation.

C.

Begin executing the rollback plan.

D.

Record the issue and proceed with the implementation.

Discussion