Question 76

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Discussion
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Jan 16, 2026
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Jan 6, 2026
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jan 25, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Jan 8, 2026
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Question 77

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Options:

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Discussion
Question 78

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Options:

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

Discussion
Question 79

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Discussion