CompTIA Updated PK0-005 Exam Questions and Answers by cassidy

Page: 19 / 28

CompTIA PK0-005 Exam Overview :

Exam Name: CompTIA Project+ Certification (2025)
Exam Code: PK0-005 Dumps
Vendor: CompTIA Certification: Project+
Questions: 386 Q&A's Shared By: cassidy
Question 76

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Discussion
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Oct 10, 2025
That's great to know. So, you think new students should buy these dumps?
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Oct 11, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 12, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Oct 2, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 1, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 77

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Options:

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Discussion
Question 78

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Options:

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

Discussion
Question 79

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Discussion