Question 68

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram

Discussion
Question 69

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

Options:

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Discussion
Question 70

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

Options:

A.

Performance

B.

Smoke

C.

Regression

D.

Unit

Discussion
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Sep 3, 2024
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Andrew
Are these dumps helpful?
Jeremiah Oct 27, 2024
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Question 71

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options:

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.