Question 12

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

Options:

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 3, 2024
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Sep 13, 2024
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Question 13

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options:

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Discussion
Question 14

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Discussion
Question 15

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Discussion