Special Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

AACE International Updated CCP Exam Questions and Answers by yaqub

Page: 7 / 13

AACE International CCP Exam Overview :

Exam Name: Certified Cost Professional (CCP) Exam
Exam Code: CCP Dumps
Vendor: AACE International Certification: AACE
Questions: 189 Q&A's Shared By: yaqub
Question 28

Questions 28

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost of manufacturing labor for the piece of equipment today?

Options:

A.

$140,000

B.

$875,000

C.

$210,000

D.

$105,000

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Aug 14, 2024
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Norah
Cramkey is highly recommended.
Zayan Oct 17, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Oct 29, 2024
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Sep 6, 2024
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 29

AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

Options:

A.

Risk analysis

B.

Benefit/Cost ratio (B/C) method

C.

Net present worth method

D.

Life cycle costs method (LCC)

Discussion
Question 30

Questions 30

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

Options:

A.

45%

B.

50%

C.

95%

D.

30%

Discussion
Question 31

If a project is said to be on a "fast track program/' the fast track method is:

Options:

A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work

B.

First completing engineering and procurement, then executing construction

C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance

D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime

Discussion
Page: 7 / 13

CCP
PDF

$36.75  $104.99

CCP Testing Engine

$43.75  $124.99

CCP PDF + Testing Engine

$57.75  $164.99