Question 12

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following is considered a measure of profitability?

Options:

A.

Rate of return

B.

Annual Dividends

C.

Total assets

D.

Annual sales

Discussion
Question 13

After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

Is the percent complete stated by the contractor correct?

Options:

A.

No, it should be 55.0%

B.

No, it should be 50.0%

C.

No, it should be 52.5%

D.

Yes, it is 60%

Discussion
Question 14

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Which statement best describes the type of information available for a design phase estimate?

Options:

A.

Home office detail, specific vendor quotes, preliminary quantities with labor and material factors applied

B.

Square footage of buildings, factored indirects, types of rides and exhibits identified, utility requirements, conceptual layouts

C.

Detailed construction drawings, quantity takeoffs, detailed labor hours and material costs applied, quotes from all major subcontractors

D.

Utility requirements, detailed building plans and (- specifications, types of rides and exhibits identified, all vendor quotes or estimates received from subcontractors

Discussion
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius (not set)
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha (not set)
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly (not set)
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby (not set)
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun (not set)
That sounds really useful. I'll definitely check it out.
Question 15

Questions 15

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs from Atlanta, GA?

Options:

A.

$40.59

B.

3

C.

$48.33

D.

33.33%