Question 32

Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)

Options:

A.

You cannot do Scrum without feature teams.

B.

Productivity may suffer when making this kind of move.

C.

Getting support from the business side first helps.

D.

Feature teams have less communication overhead.

E.

With feature teams, it is easier to calculate the productivity per team.

Discussion
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Question 33

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

Options:

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Discussion
Question 34

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.

Discussion
Question 35

Who has the final say on the order of the Product Backlog?

Options:

A.

The Development Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Stakeholders.

E.

The CEO.

Discussion