Question 52

Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?

Options:

A.

Business case

B.

Plans

C.

Change

D.

Progress

Discussion
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Sep 26, 2024
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 31, 2024
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Aug 12, 2024
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Question 53

How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?

Options:

A.

The work packages are defined by the team manager and supported by a team plan

B.

the work packages provided by the project manager are agreed by the team manager

C.

The team plans are checked by project assurance against the work packages

D.

The stage plan covering the work packages is created with input from the team manager

Discussion
Question 54

What statement describes how the project manager should ensure effective communication within a project?

Options:

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Discussion
Question 55

Which describes a time-driven control?

Options:

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Discussion
Page: 13 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99