Question 24

When should the level of tailoring be defined?

Options:

A.

During the initiation stage

B.

When reviewing what has been learned to date

C.

As a response to issues and risks experienced

D.

Before the project is triggered by the project mandate

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 14, 2024
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Question 25

Which describes a project benefit?

Options:

A.

A specialist product of the project

B.

The result of a change derived from using the project's products

C.

An uncertain result caused by project actions

D.

A measurable improvement resulting from an outcome

Discussion
Question 26

Who represents the three project interests on a project?

Options:

A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Discussion
Question 27

According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

Options:

A.

Project board, project manager and project assurance roles

B.

Directing, managing and delivering levels

C.

Business, user and supplier interests

D.

Corporate, programme management or the customer parties

Discussion
Page: 6 / 34
Title
Questions
Posted

Prince2-Foundation
PDF

$36.75  $104.99

Prince2-Foundation Testing Engine

$43.75  $124.99

Prince2-Foundation PDF + Testing Engine

$57.75  $164.99