An internal factor to consider when tailoring PRINCE2 to a specific project environment is "The organization's procedures." Tailoring must take into account internal practices, procedures, and organizational culture to ensure that the project management approach aligns well with internal governance and can be effectively integrated within the organizational context.References: (PRINCE2® 7 Foundation Handbook, AXELOS)QUESTION NO: 448
What should the ‘organizing’ practice address?
A. How to meet the user's requirements of the project products
B. Which members of the project management team should report to whom
C. What might go wrong that could affect the achievement of the business objectives
D. who will be impacted by the change and how they will need to transition the new capabilities
Answer: B
The ‘organizing’ practice in PRINCE2 should address how the project management team is structured, specifically detailing which team members should report to whom. This practice ensures clear lines of communication and responsibility within the project team, facilitating effective management and decision-making processes.References: (PRINCE2® 7 Foundation Handbook, AXELOS)