Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated CA0-001 Exam Questions and Answers by jameson

Page: 7 / 19

PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: jameson
Question 28

Which statement is true about Bottom-up estimating?

Options:

A.

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.

B.

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.

C.

Using project characteristics (or parameters) in a mathematical model to predict costs.

D.

Cost of quality can also be used to prepare the schedule activity cost estimate.

Discussion
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 9, 2024
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 14, 2024
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Question 29

Who is responsible for the creation of the final project plan?

Options:

A.

Project Manager

B.

Team Leader

C.

Sponsor

D.

Project Team

Discussion
Question 30

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?

Options:

A.

Parametric estimating

B.

Funding limit reconciliation

C.

Reserves analysis

D.

None of the above

Discussion
Question 31

Create Procurement document is done in _______.

Options:

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Discussion
Page: 7 / 19

CA0-001
PDF

$36.75  $104.99

CA0-001 Testing Engine

$43.75  $124.99

CA0-001 PDF + Testing Engine

$57.75  $164.99