PMI CA0-001 Exam Overview :

Exam Name: Certified Associate in Project Management (CAPM) Certification
Exam Code: CA0-001 Dumps
Vendor: PMI Certification: CAPM
Questions: 525 Q&A's Shared By: jameson
Question 28

Which statement is true about Bottom-up estimating?

Options:

A.

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.

B.

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.

C.

Using project characteristics (or parameters) in a mathematical model to predict costs.

D.

Cost of quality can also be used to prepare the schedule activity cost estimate.

Discussion
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Aug 29, 2024
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 26, 2024
Thanks for the recommendation! I'll check it out.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Question 29

Who is responsible for the creation of the final project plan?

Options:

A.

Project Manager

B.

Team Leader

C.

Sponsor

D.

Project Team

Discussion
Question 30

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?

Options:

A.

Parametric estimating

B.

Funding limit reconciliation

C.

Reserves analysis

D.

None of the above

Discussion
Question 31

Create Procurement document is done in _______.

Options:

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Discussion