Question 36

If a project with a SPI of 0.8, what you tell?

Options:

A.

The project is running ahead of the schedule

B.

The project is running behind of the schedule

C.

Resources assigned to the project cost 1.8 units

D.

None

Discussion
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Sep 22, 2024
That's great to hear. I am going to try them soon.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Sep 11, 2024
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Sep 14, 2024
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Question 37

The end of the project comes after which of the following?

Options:

A.

Project charter

B.

Final deliverable

C.

Schedule

D.

QA activities are done

Discussion
Question 38

_________ is always the lowest risk for the buyer if the scope of work is not well defined.

Options:

A.

Cost plus incentive fee

B.

F'xed P|ice

C.

Time and material

D.

"'s^ 's nc* 'elated to price

Discussion
Question 39

Who has the responsibility for Plan Quality?

Options:

A.

Project manager

B.

QA manager

C.

Project planner

D.

Team lead