Question 20

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

Options:

A.

Create WBS

B.

Vei*

C.

Value analysis

D.

Control Scope

Discussion
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 15, 2024
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Question 21

Which process group is for detailed resource assignments and responsibilities?

Options:

A.

Human resources management plan

B.

Project charter

C.

Aplan

D.

Project management plan

Discussion
Question 22

Which of the following is NOT input of Identify Risks?

Options:

A.

Project Charter

B.

Stakeholder Register

C.

Pis'* Management Plan

D.

Activity Cost Estimates

Discussion
Question 23

Which is not the tools and techniques used in Contract Administration:

Options:

A.

Contract change control system

B.

Contract negotiation

C.

Payment system

D.

Performance rating

Discussion