Question 56

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

Options:

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Discussion
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Aug 20, 2024
Me too. They're a lifesaver!
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 20, 2024
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 31, 2024
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 9, 2024
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 57

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

Options:

A.

Interrelationship digraphs

B.

Tree diagram

C.

Affinity diagram

D.

Network diagram

Discussion
Question 58

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Discussion
Question 59

A key benefit of the Manage Communications process is that it enables:

Options:

A.

The best use of communication methods.

B.

An efficient and effective communication flow.

C.

Project costs to be reduced.

D.

The best use of communication technology.

Discussion