Question 76

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Discussion
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Aug 30, 2024
That’s great!!! I’ll definitely give it a try. Thanks!!!
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Aug 12, 2024
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Question 77

Which tool or technique is used in validating the scope of a project?

Options:

A.

Facilitated workshops

B.

Interviews

C.

Inspection

D.

Meetings

Discussion
Question 78

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

Options:

A.

mitigate

B.

accept

C.

transfer

D.

avoid

Discussion
Question 79

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control