Question 140

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

Options:

A.

Matrix - strong

B.

Matrix - balanced

C.

Virtual

D.

Functional

Discussion
Question 141

Which process uses expert judgment to manage project resources?

Options:

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Manage Team

D.

Both A and B

Discussion
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Sep 16, 2024
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Aug 8, 2024
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Sep 24, 2024
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Question 142

What risk response strategy involves removing high- risk scope elements from a project?

Options:

A.

Transfer

B.

Avoid

C.

Exploit

D.

Accept

Discussion
Question 143

What is the key benefit of the Monitor Stakeholder Engagement process?

Options:

A.

Ensures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts

B.

Ensures that the project includes all the work required and only the work required—to complete the project successfully

C.

Increases the probability and/or impact of positive risks, and decreases the probability and/or Impact of negative risks or issues

D.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves

Discussion
Page: 35 / 84
Title
Questions
Posted

CAPM
PDF

$36.75  $104.99

CAPM Testing Engine

$43.75  $124.99

CAPM PDF + Testing Engine

$57.75  $164.99