Question 64

Your company's new CEO has set an aggressive target and informed everyone that the target needs to be met by all means in order for the company to be able to realize benefits and avoid bankruptcy. What is the best management approach that the portfolio manager should take in this case?

Options:

A.

Directing

B.

Advising

C.

Leading

D.

Supporting

Discussion
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Oct 23, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Oct 10, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 15, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Oct 24, 2025
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 65

After a strategic change is managed and finalized, you as a portfolio manager, are expected to document changes to the portfolio components attributes. Which of the following is the document in which you document these changes?

Options:

A.

Portfolio Strategic Plan updates

B.

Portfolio updates

C.

Portfolio Management Plan updates

D.

Portfolio Process Assets updates

Discussion
Question 66

For governments worldwide, you normally have a lot of people reluctant to change and to using new technology tools especially for communication. You are managing a governmental portfolio and planning for a transformational endeavor. You are currently depicting the various communication media and methods to be used, where is this information normally used?

Options:

A.

Communication Matrix

B.

Stakeholder Communication Strategy Matrix

C.

Stakeholder Groups

D.

Stakeholder Matrix

Discussion
Question 67

Assume you are the portfolio manager for a telecommunications company. Your company was about to launch a new and easy to use smart phone with more features than any existing phones on the market at a lower price. However, although the phone was due to market in five days, the Federal Communications Commission issued today a regulation that would make your new phone not available for use in airplanes. Thus additional work must be done, and your executives are wondering whether a new phone should be developed for this new feature. You are ensuring that if a new phone is developed, or if the almost completed product is not to be marketed, there is still alignment to the organization's strategy. As you complete an analysis of alternatives, you also should ensure results of the analysis are reflected in the:

Options:

A.

Benefits realization plan

B.

Portfolio process assets

C.

Portfolio roadmap

D.

Portfolio performance plan

Discussion