Question 12

A business analyst (BA) is preparing a requirement package for access management system. A state diagram foe entity 'User* has been prepared. The BA wants to check the completeness of requirements by comparing different models. Which diagram should be used with a state diagram to verity that all functions are defined to work with entity "User" for the different roles?

Options:

A.

Sequence diagram

B.

Functional diagram

C.

Use case diagram

D.

Data flow diagram

Discussion
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Aug 20, 2024
Me too. They're a lifesaver!
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 9, 2024
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Oct 2, 2024
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Question 13

Several commercial-off-the-shelf (COTS) software packages exist that would enable the business analyst (BA) to meet the needs of the business. For the potential deign options, the Ba included one of the COTS packages as a solution approach What kind of solution approach is this?

Options:

A.

Outsource

B.

Exploit

C.

Create

D.

Purchase

Discussion
Question 14

A business analyst (BA) on a project is in the process of validating requirements and finds that there is a high degree of uncertainty related 10 one of the assumptions being true. The BA adds the assumption to the risk register and performs a fun risk analysis to handle this situation. What type of strategy is in place if the organization is risk-averse?

Options:

A.

Acceptance

B.

Transfer

C.

Avoidance

D.

Mitigation

Discussion
Question 15

Due to the complexity of a project the project board a concerned that the business analyst (BA) will not be able to ensure all requirements are verified. What toed can the BA present to the project board to mitigate their concern?

Options:

A.

Data model

B.

Use case diagram

C.

Risk register

D.

Business analysis checklist