Question 12

For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a

Options:

A.

SoW.

B.

spare ad sheet

C.

worksheet

D.

database

Discussion
Question 13

Which two of the following are ADVANTAGES of aerial pathways? (Select two options.)

Options:

A.

Quick to install

B.

Has a low initial installation cost

C.

Affect the aesthetic appearance of the property

D.

Economical over a long life

E.

Readily accessible for maintenance

Discussion
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Sep 24, 2024
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 24, 2024
Absolutely. It's a great way to increase your chances of success.
Question 14

During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?

Options:

A.

Review and update the detailed stakeholder list

B.

Review and update the stakeholder engagement plan

C.

Execute the component project's communications management plan

D.

Update the risk register.

Discussion
Question 15

During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.

At this stage, what is expected during the post-review session organized by the program manager?

Options:

A.

Earned value (EV) report

B.

Customer sign-off

C.

Benefits register updates

D.

Feedback and lessons learned