Special Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

BICSI Updated RCDDv14 Exam Questions and Answers by effy

Page: 2 / 10

BICSI RCDDv14 Exam Overview :

Exam Name: BICSI Registered Communications Distribution Designer - RCDDv14
Exam Code: RCDDv14 Dumps
Vendor: BICSI Certification: RCDD Certification
Questions: 288 Q&A's Shared By: effy
Question 8

A two-year program is coming to an end Many of the initial governance board members have moved from their current posts or left the company Several new members have joined but have a shod association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.

How should the program manager handle this situation?

Options:

A.

Review the final program outcome with the program sponsor

B.

Prepare a program change request utilizing new board member input

C.

Review the strategic plan and benefits management plan with the board

D.

Present the final program status, costs, and schedule reports

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 25, 2024
That makes sense. What makes Cramkey Dumps different from other study materials?
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Aug 29, 2024
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Question 9

The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.

In this situation, what should the program manager change about the risk management plan?

Options:

A.

Allow the component project manager to delegate risk management responsibilities

B.

Assign the resolution of project-level risks to the component project manager

C.

Include risk escalation policies and procedures in the risk response plan

D.

Increase flexibility with risks that require a risk response

Discussion
Question 10

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved

What should the program manager do to ensure benefits realization?

Options:

A.

Conduct a program performance analysis based upon the deviation, and update the program business case to reflect the schedule delay

B.

Inform the program sponsor and the steering committee of the delay, and validate the program business case

C.

Analyze the impact of the delay, review risks, identify any corrective actions, and update the benefits management plan

D.

Update the program schedule, and escalate the issue to the program management office (PMO) to accelerate shipyard work.

Discussion
Question 11

A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

Options:

A.

Project submittal approval process

B.

RFI process

C.

Payment procedures

D.

Punch List process

E.

Project start and completion dates

Discussion
Page: 2 / 10

RCDDv14
PDF

$36.75  $104.99

RCDDv14 Testing Engine

$43.75  $124.99

RCDDv14 PDF + Testing Engine

$57.75  $164.99