BICSI Updated RCDDv14 Exam Questions and Answers by coby

Page: 8 / 10

BICSI RCDDv14 Exam Overview :

Exam Name: BICSI Registered Communications Distribution Designer - RCDDv14
Exam Code: RCDDv14 Dumps
Vendor: BICSI Certification: RCDD Certification
Questions: 288 Q&A's Shared By: coby
Question 32

A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program's benefits sustainment and transition plan What should the program manager do to create this plan?

Options:

A.

Identify key measures to compare expected benefits in the benefits management plan with actual performance once benefits sustainment and program transition starts

B.

Assign creation of the benefits sustainment plan to the organization responsible for monitoring and controlling the sustainment period

C.

Interview stakeholders and revise the benefits management plan to provide new insight into the program's execution and benefits sustainment period

D.

Update the benefits management plan, and provide a copy to the organization responsible for measuring the sustainment period

Discussion
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Aug 30, 2024
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Oct 22, 2024
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Aug 29, 2024
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Question 33

An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

Options:

A.

Accept the assignment, identify the skill gaps and request training

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager

D.

Reject the assignment because of fear of failure and resulting negative career impact

Discussion
Question 34

A company is evaluating the implementation of enterprise resource planning (ERP) software.

The program manager performs an analysis to confirm the program's feasibility

What other important step should the program manager complete^

Options:

A.

Development of the program's vision statement

B.

Review of strategic goals against any external environmental factors

C.

Identification and documentation of the initial risks for ERP software Implementation

D.

Mapping of the financial benefits to the ERP software's functionality

Discussion
Question 35

A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years

What is the expected time of delivery?

Options:

A.

1.25 years

B.

1 50 years

C.

175 years

D.

1 00 years

Discussion
Page: 8 / 10

RCDDv14
PDF