Question 12

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Options:

A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Discussion
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Aug 29, 2024
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 25, 2024
That makes sense. What makes Cramkey Dumps different from other study materials?
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Inaaya
Are these Dumps worth buying?
Fraser Oct 9, 2024
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Sep 24, 2024
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Question 13

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

Options:

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.

Replace the relationship from 'B’ to 'C’ with SSO

C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort

Discussion
Question 14

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Options:

A.

ahead of schedule

B.

on schedule

C.

complete

D.

behind schedule

Discussion
Question 15

What is a critical path method schedule?

Options:

A.

List of work to be accomplished by responsible party and when it is to be accomplished

B.

The timeline of the riskiest work

C.

A graphical means of showing the important work

D.

A network diagram of logically interconnected activities

Discussion