Question 16

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

Questions 16

Options:

A.

09-28-01.

B.

09-08-01.

C.

09-15-01.

D.

09-18-01.

Discussion
Question 17

Identify the minimum project duration.

Questions 17

Options:

A.

20 months.

B.

16 months.

C.

19 months.

D.

21 months.

Discussion
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Aug 20, 2024
Me too. They're a lifesaver!
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 2, 2024
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 28, 2024
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Question 18

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

Options:

A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects

Discussion
Question 19

Free float is the

Options:

A.

Difference between the early dates and late dates of an activity.

B.

Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.

C.

Difference between the early finish dates and late finish dates of an activity.

D.

Difference In float value of the critical path activities and the float value of the specific activity being analyzed.

Discussion
Page: 4 / 11

PSP
PDF

$36.75  $104.99

PSP Testing Engine

$43.75  $124.99

PSP PDF + Testing Engine

$57.75  $164.99